ANANTARA RESORT & SPA – CENTRAL PLANT AREA, MARINA ISLAND

The engineering infrastructure of a luxury island resort is fundamental to its uninterrupted operation. At Anantara Resort & Spa, Marina Island, SLP Engineering undertook a complex building services project involving the central plant area, staff accommodation and supporting infrastructure.
Project:Anantara Resort & Spa – Central Plant Area
Segments:Resorts, Wellness & Recreation
Location:Marina Island, Maldives
Completion:2024
Architect:
GX Associates (Pvt) Ltd
Building contractor:
Inoca Engineering
M&E Engineer:
SLP Engineering (Pvt) Ltd
Our Scope of Work
  • Delivered electrical and ELV infrastructure services.
  • Undertook plumbing and firefighting infrastructure works.
  • Installed air-conditioning and ventilation systems for central plant rooms and staff accommodation.
  • Coordinated the removal of existing services without disrupting resort operations.
Challenges
  • Fast-track project and 18-month contract
  • Demolishing of existing services without interrupting resort operations

Keeping a luxury island destination running, without missing a beat

The engineering infrastructure of a luxury island resort is fundamental to its uninterrupted operation. At Anantara Resort & Spa, Marina Island, SLP Engineering undertook a complex building services project involving the central plant area, staff accommodation and supporting infrastructure.

The project required the delivery of electrical and Extra Low Voltage (ELV) infrastructure, plumbing and firefighting infrastructure, as well as air-conditioning and ventilation systems for central plant rooms and staff accommodation.

One of the principal challenges was the demolition of existing services without interrupting resort operations. Working within an 18-month contract programme, SLP Engineering had to coordinate the replacement and installation works with the operational demands of an active hospitality environment.

The result demonstrates the importance of careful planning, technical coordination and engineering execution when upgrading essential infrastructure in an operating resort.

Why this building matters

Working within an operational resort is fundamentally different from delivering services in a new development. Existing infrastructure must be carefully assessed, removed and replaced while maintaining the continuity of guest services and resort operations.

Anantara demonstrates SLP Engineering’s ability to manage technically demanding infrastructure works in a live hospitality environment. The project highlights a particularly important capability: delivering essential engineering upgrades while allowing the business they support to continue operating

Our Scope of Work
  • Delivered electrical and ELV infrastructure services.
  • Undertook plumbing and firefighting infrastructure works.
  • Installed air-conditioning and ventilation systems for central plant rooms and staff accommodation.
  • Coordinated the removal of existing services without disrupting resort operations.
Challenges
  • Fast-track project and 18-month contract
  • Demolishing of existing services without interrupting resort operations

Get in Touch with Our Team