CINNAMON RED, COLOMBO

Every hotel needs air conditioning, power, water, fire protection and a pool that works. A city hotel needs all of it in a building with almost no space to spare. Two things made Cinnamon Red challenging: the programme was fast track, and the areas set aside for mechanical and electrical services were limited.
Project:Cinnamon Red
Segments:Hotels
Location:Colombo, Sri Lanka
Completion:2014
Architect:
Design Team 3 (Pvt) Ltd
Building contractor:
Sanken Construction (Pvt) Ltd
M&E Engineer:
SLP Engineering Limited (design and build)
Our Scope of Work

SLP Engineering’s scope included:

  • Electrical services
  • Public health services
  • HVAC services
  • Fire-fighting systems, including sprinkler, hydrant and fire suppression installations
  • Swimming pool services
  • Energy audit services

The combined scope brought together the building’s essential engineering systems with an additional focus on energy performance.

Challenges

• Fast-track project and Limited MEP areas

Every hotel needs air conditioning, power, water, fire protection and a pool that works. A city hotel needs all of it in a building with almost no space to spare. Two things made Cinnamon Red challenging: the programme was fast track, and the areas set aside for mechanical and electrical services were limited.

The building in three numbers

  • 27 storeys
  • 214 keys, plus 1 suite
  • 1 rooftop pool and gym

Why this building matters

Cinnamon Red put a 27-storey city hotel in the middle of Colombo 03. It carries a rooftop pool and gym above the city. The hotel was a vital and stylish addition to Colombo’s offering of city and business hotels. And it continues to be a popular choice to-date.

Our Scope of Work

SLP Engineering’s scope included:

  • Electrical services
  • Public health services
  • HVAC services
  • Fire-fighting systems, including sprinkler, hydrant and fire suppression installations
  • Swimming pool services
  • Energy audit services

The combined scope brought together the building’s essential engineering systems with an additional focus on energy performance.

Challenges

• Fast-track project and Limited MEP areas

Get in Touch with Our Team